WHAT WE BUILD
We build the infrastructurebehind a solar park.
Civil, mechanical and electrical works with our own crews and our own plant. One partner from the first stake to energisation.
THE FOUR AREAS
Three trades on site,one that holds them together.
AREA 01Civil works

Site preparation, internal access roads, cable trenching, foundations for substations and inverters, final reinstatement.
It is the work nobody photographs and that determines everything else: a trench off level or an access road that gives way in the rain will stop the assembly long before any supply delay does.
- SITE PREPARATION
- ACCESS ROADS
- TRENCHING & BACKFILL
- FOUNDATIONS
- REINSTATEMENT
AREA 02Mechanical works

This is the visible part: thousands of piles driven to controlled verticality, fixed structures assembled row by row, modules laid and torqued to nominal values.
On a hundred-megawatt field the difference between one crew and another is not first-day speed: it is holding the same geometry on day one hundred and forty, when it rains and the ground gives way.
- PILE DRIVING
- FIXED STRUCTURES
- TRACKERS
- MODULE INSTALLATION
- TORQUE CONTROL
AREA 03Electrical works

Cable laying in trench and on tray, DC and AC wiring, inverter connection, MV/LV substations, testing and commissioning.
This is where a plant's reliability for the next thirty years is decided. Every string is tagged, tested and recorded: if a contact is wrong we want to know before handover, not in the third winter.
- CABLE LAYING
- DC/AC WIRING
- INVERTERS
- MV/LV SUBSTATIONS
- COMMISSIONING
AREA 04Execution and management

Project and construction management, site management, materials logistics, safety and quality control. This is the layer above the three disciplines, and it decides whether they advance together or wait on each other.
FGM does not supply labour to somebody else's site: it takes on a defined scope and delivers it. That means one contact for progress, one safety plan and one party accountable when something goes wrong.
- PROJECT MANAGEMENT
- SITE MANAGEMENT
- LOGISTICS
- HSE
- QUALITY CONTROL
THE SEQUENCE
Eleven phases,always in the same order.
This is the sequence we work to on every field, from the first stake to handover. On the home page the same sequence is shown photograph by photograph.
- 01SURVEYThe field exists before the machines do.
- 02PILE DRIVINGSteel foundations.
- 03EXCAVATIONWhat matters will never be seen.
- 04CABLE ROUTESKilometres in a straight line.
- 05CABLE PULLINGEvery metre has a number.
- 06LOGISTICSMaterial arrives before it is needed.
- 07STRUCTURESThe field takes shape.
- 08MODULES154,000 times the same precision.
- 09DC WIRINGReliability lives in the details.
- 10SUBSTATIONS & INVERTERSCurrent becomes energy.
- 11HANDED OVERThen the silence begins.
- →2.4 GWp installedThe film begins
THE PROOF
Not a list of intentions.A list of what we have built.
Swan
140MWp- LOCATION
- Zwanenburg, The Netherlands
- CLIENT
- Goldbeck Solar
- YEAR
- 2024 · COMPLETED
From the reference list, updated with every site handed over.
OPEN THE REFERENCE LISTDOCUMENTS
What you cancheck for yourself.