Parco solare di Lelystad, Paesi Bassi — 42 MWp realizzati da FGM Solar
2 GWp installed· 10 nations· 4 continents· since 2013

We build solar parks. From topography to energization. 

One point of contact for civil, mechanical and electrical works. From the first stake to the energized substation.

13YEARS ON SITE
10NATIONS · 4 CONTINENTS
2GWpINSTALLED
140MWpLARGEST PROJECT
WHERE WE HAVE BUILT

Ten countries,
one way of working.

Every dot is one of our sites, sized by installed capacity. Hover a dot to read its name; the full reference list runs to ninety-five plants.

Map of FGM Solar construction sites across Europe: each dot is a plant, its area proportional to installed capacity.SALTERAS — 130 MWp — SpagnaSALTERAS130 MWp · SpainSCHÖNERMARK — 80 MWp — GermaniaSCHÖNERMARK80 MWp · GermanyBELLINGWOLDE — 74 MWp — Paesi BassiBELLINGWOLDE74 MWp · NetherlandsHOLLANDSCHEVELD — 51 MWp — Paesi BassiHOLLANDSCHEVELD51 MWp · NetherlandsOSSENDRECHT — 51 MWp — Paesi BassiOSSENDRECHT51 MWp · NetherlandsLELYSTAD — 42 MWp — Paesi BassiLELYSTAD42 MWp · NetherlandsBAVELSE BERG — 37 MWp — Paesi BassiBAVELSE BERG37 MWp · NetherlandsHECHTHAUSEN — 10 MWp — GermaniaHECHTHAUSEN10 MWp · Germany
  • Netherlands5 · 255 MWp
  • Spain1 · 130 MWp
  • Germany2 · 90 MWp
IN PROGRESSCOMPLETEDAREA ∝ CAPACITY

Coordinates are those of the locality, not of the plant centre. The map shows sites with a full project page.

WHAT WE DO

One contractor,
three trades.

01

Mechanical works

Pile driving, mounting structures and installing modules. The core of our work, and the part you can see.

02

Civil works

Site preparation, internal haul roads, cable trenching. What matters most will never be seen again.

03

Electrical works

DC and AC cabling, inverter connection, MV/LV stations through to energisation.

CLIENTS

We don't introduce ourselves.
They do it for us.

We work as specialist subcontractor for the EPCs and developers behind Europe's largest parks. Every name can be checked on the project page, against the client's own source.

SURVEY — The field exists before the machines.
01SURVEY

The field exists before the machines. 

GPS RTK, staking out, level checked point by point. Every pile has an address before the steel arrives.

GPS RTK · BASELINE · LAYOUT
PILE DRIVING — Steel foundations.
02PILE DRIVING

Steel foundations. 

Thousands of piles driven at 90,0°. Up to 400 a day per crew, one by one, never losing the row alignment.

VERTICALITY 90,0° · 950 J HAMMER · 400 PILES/DAY
EXCAVATION — What matters will never be seen.
03EXCAVATION

What matters will never be seen. 

Open trenches between the rows, depth checked before backfilling. After that, to check, we dig again.

CONTROLLED TRENCH · CHECKED LEVEL
CABLE DUCTS — Kilometres in a straight line.
04CABLE DUCTS

Kilometres in a straight line. 

A single backbone can carry twelve kilometres of cable. A detour made for convenience is paid for over twenty years.

MT BACKBONE · SAND BED · WARNING TAPE
CABLE LAYING — Every metre has a number.
05CABLE LAYING

Every metre has a number. 

Reels, pulls, joints. The cable goes into the trench already tagged and already tested: nothing is improvised on site.

TRENCH LAYING · TAGGING · INSULATION TESTS
LOGISTICS — The material arrives before it is needed.
06LOGISTICS

The material arrives before it is needed. 

Rails, modules and bolts distributed along the rows. The perfect grid is not order: it is time no one wastes.

~2.700 RAILS · ROW DISTRIBUTION
STRUCTURES — The field takes shape.
07STRUCTURES

The field takes shape. 

Beams, purlins, clamps. Sixty people assembling the same geometry two kilometres apart.

TILT 25° · TORQUE TIGHTENING · ROW TOLERANCE
MODULES — 154.000 times the same precision.
08MODULES

154.000 times the same precision. 

Each module weighs thirty-five kilos and must be placed, aligned and clamped without ever touching the glass with a hand.

650 Wp MODULES · PAIRS INSTALLATION · VISUAL CHECK
DC WIRING — Reliability lives in the details.
09DC WIRING

Reliability lives in the details. 

Strings, connectors, ties. A bad connection is not visible on day one: it shows up in the third winter.

DC CONNECTIONS · STRING MEASUREMENT · THERMOGRAPHY
SUBSTATIONS AND INVERTERS — Current becomes energy.
10SUBSTATIONS AND INVERTERS

Current becomes energy. 

Inverters, switchboards, MT/BT substations, commissioning tests. The field stops being a construction site and becomes a plant.

MT/BT SUBSTATIONS · SCADA · COMMISSIONING
DELIVERED — Then the silence begins.
11DELIVERED

Then the silence begins. 

Thirty years of production without anyone having to come back. The best work is the one you no longer see.

READY TO PRODUCE · 30 YEARS OF USEFUL LIFE · FGM SOLAR
ONE SITE, SIX MONTHS

Bellingwolde,
May to October.

Seventy-four megawatts in the north of the Netherlands, photographed by drone every month. Drag to move through the build.

La prima trincea aperta nel campo di Bellingwolde, maggio 2025La posa dei cavidotti attraverso il campo di Bellingwolde, giugno 2025Le strutture montate prima della posa dei moduli, luglio 2025I primi moduli posati sulle tavole a Bellingwolde, fine luglio 2025Montaggio dei moduli bifacciali in corso a Bellingwolde, agosto 2025Il campo di Bellingwolde quasi completo, agosto 2025Vista aerea del parco di Bellingwolde, settembre 2025Bellingwolde nel paesaggio della Groninga, settembre 2025Il parco di Bellingwolde completato, ottobre 2025
TECHNICAL DATA
THE SITE

Thirteen years,
seen from above.

We do not use stock photos. Every image on this site was taken on one of our sites, by the people working there.

REFERENCES
PROJECTS
THE EVIDENCE

What you can
check for yourself.

Certified management system
Management system certified by TÜV AUSTRIA GMBH to EN ISO 9001 (20100233018318), EN ISO 14001 (20104233018319), ISO 45001 (20116233018320)
EN ISO 9001
20100233018318
EN ISO 14001
20104233018319
ISO 45001
20116233018320
TÜV AUSTRIA GMBH
NEXT PROJECT

Your plant deserves
a flawless execution.

REQUEST A PROPOSAL