94,000 modules on a landfill that is still in use, installed without a single hole in the sealing membrane: the hardest project in the portfolio.

Completed37 MWpGOLDBECK SOLAR / Rooftop Energy (Groendus)51°35′N · 4°49′E

The site

In operation since March 2021 · officially opened on 16 September 2021

Bavelse Berg is the largest solar park on a landfill site in the Netherlands: 37 MWp and around 94,000 bifacial modules on an artificial hill on the edge of Breda that is still, in part, an operating landfill and biogas plant.

The technical constraint that governed the whole site is a membrane: the body of the landfill is sealed by a separation liner crossed by gas extraction pipes, valves, water drains and cables. None of it could be pierced or damaged. Almost every component of the support structure was therefore purpose-designed — a rail system that lets modules be assembled and slid into place, anchored at single points, adapting to the irregular slopes of the hill, with the panels raised between one and two and a half metres above the ground.

The semi-transparent bifacial modules let through enough light for grass to grow under the rows: the site still supports sheep grazing and natural habitat. The park went into operation in March 2021 and was officially opened on 16 September of the same year.

OUR WORK ON SITE

3
Mechanical worksPile driving, fixed structure assembly and module installation with controlled torque.Done
Civil worksSite preparation, internal access roads and cable trenching.Done
Electrical worksCable laying, DC and AC wiring, inverter connection and MV/LV substations.Done

TECHNICAL DATA

CLIENT
GOLDBECK SOLAR / Rooftop Energy (Groendus)
PERIOD
In operation since March 2021 · officially opened on 16 September 2021
Capacity
37 MWp
Modules
Approx. 94,000 bifacial Jinko
Inverters
Huawei, decentralised configuration
Structures
Purpose-designed rail system, no penetration of the liner
Module height
1–2.5 m above ground
Location
Bavelse Berg, Breda
EPC
GOLDBECK SOLAR
Client
Rooftop Energy (now Groendus)
Site owner
Sweco
In operation
March 2021
CO₂ avoided
Approx. 15,000 t per year
Households supplied
Approx. 10,000

Where

Bavelse Berg, Breda
From the field

5 photographs, taken by the people who built it.

NEXT PROJECT

Hechthausen

10 MWp · Germany

Open the project

Have a field to build? We have the crews.

A plant like this? let's talk